Locating in the west of Isfahan, the construction is in two phases with an area of 47 hectares.
The project manager announced that many sectors have been fully constructed including: mechanical-electrical installations, the scaffolding for hall of "Allameh Majlesi", indoor and outdoor manholes, containers for drinking water as well as non-drinking water, pump house, rest rooms, and access to enter and exit.
"Other section completed are as following: roads and spaces inside the exhibition, the bridges at the two sides of "Allameh Majlesi" hall, office building, mechanical power plant, electricity house, unloading ducks, and green spaces", Hosseini made the remarks.
Reminding that the design and construction of this international exhibition covers both traditional and modern atmosphere, he added: Some facades of the complex are ornamented with bricks, demonstrating the old architecture of Isfahan.